SRN
  • Home
  • News
    • Newslines
    • Skyline Voices
    • Skyline Ridge Runners
    • Ridge Runner Advertising
  • Calendar
    • Spring meeting 2023
  • Topics
    • Resource Directory
    • History of Skyline >
      • Story-telling videos
      • Skyline History Project
    • Home Life
    • Land Stewardship
    • Garden, Animals & Forest
    • Public Roads
    • Life on the Hill
  • About
    • Board
    • Bylaws
    • Boundary Map
    • Annual Report
    • Volunteer Opportunities
    • Contacts
    • SRN History
  • Grange
  • Be Prepared
  • SOLVE

Revised Plans for Cornelius Pass Road Improvement, May 2015

By Bruce Penney (with additional reporting by Catherine Dalziel)

The Cornelius Pass Road improvement project is on a budget roller coaster.  This update summarizes project background, reviews current project status, and identifies remaining open issues.

Representatives of Multnomah County Road Services met with the Community Advisory Committee (CAC) on May 7th at the Skyline Grange, to update members on project status for the Cornelius Pass Road Safety Improvement Project (CPRSI). Mike Pullen, Public Outreach for Multnomah County reported that $8.5 million, almost 90% of the original budget, was reallocated last year by the Oregon Legislature and dispersed to other “hammer ready” projects in need of immediate funding. 

Earlier this year, Multnomah County secured additional funds from ODOT for completion of the design work. Due to funding limitations, the signaled intersection at NW Skyline Blvd. and improvements at Sheltered Nook have been dropped from the project. A public open house is planned for later in 2015 to share the revised designs.

Project Background

Under the original budget, the county proposed spending so much on a Skyline roundabout that, even with a $9.5 million legislative appropriation, dangerous 8th Avenue curves and Tunnel/Switchback curves would have had no improvements at all.  A Community Advisory Committee (CAC) reviewed current accident data and identified three priority areas together with a group of smaller improvements: 1. 8th Avenue curves, 2. Tunnel/Switchback curves, and 3. Traffic light at Skyline.

The original $9.5 million appropriation included $1 million for design and $8.5 million for construction.  When funding was re-allocated to other projects, members of the legislative agreed to restore funding when Cornelius Pass Road was shovel-ready.  However, this agreement never materialized and construction funding was eliminated.  Now the project is re-starting with a reduced scope and smaller anticipated budget.  

Project Status

Design work is proceeding, but there is no currently-appropriated construction budget.  A reduced legislative appropriation of $4M is anticipated, which would fund projects at 8th Avenue and the Tunnel/Switchback curves, but not fund the more expensive Skyline interchange.  Major changes at the Skyline interchange and improvements at Sheltered Nook have therefore been deleted.  Design would continue through early 2017 with construction in late summer 2017.  

Ranked in budget order, components of the April 2015 project scope are:

S Curves    SC3        770,000 
8th Ave    8thAVE3        490,000 
Variable message signs    OCST10        400,000 
Boyd's Lower Driveway    SC4        340,000 
Barrier and Guardrail upgrades    OCST6        300,000 
Corridor Signage    OCST1        270,000 
Vehicle Pullouts    OCST2        200,000 
Reduce pavement drop offs    OCST9          50,000 
Kaiser Rd flashing beacon    KR2          40,000 
Curves South of Plainview    PR1          30,000 
Kaiser Rd Signage + clearing    KR1          10,000 


Construction Cost Sub-Total         2,900,000 
Remaining Design Work            750,000 
Right of Way              50,000 
Construction Administration            290,000 
Total        3,990,000 

Open Issues

With much of the CAC’s original process assuming an $8.5 million construction budget, most discussions focused on the top three safety priorities (8th Avenue, Tunnel Curves, Skyline).  Smaller budget items had relatively little discussion.  Now, with the budget slashed and Skyline intersection improvements off the table, smaller items, such as the variable messaging sign and vehicle pullouts, may deserve more scrutiny.  

At the May 7, 2015, project update meeting, a number of community members spoke in favor of improved guardrails.  Citizens noted that the May 6 fatality accident was at an area with steep embankment, long dropoff, and absolutely no guardrail protection.  Some CAC members expressed concern that combined $600,000 budgeted for variable messaging signs and poorly defined pullouts might yield greater safety benefits if spent on guardrails instead.  

Although the county plans to proceed with sign and turnout design, CAC members requested that a commensurate parallel design effort evaluate guardrail options.  CAC members also requested that results of these design efforts be presented for CAC review at a subsequent meeting.  Anticipated budget appropriations will not fund CAC safety priorities and will not meet current or anticipated traffic safety requirements.

Ridge Runner July, '15

News

Topics

Calendar
Newsline
Ridge Runner
Advertising
Skyline History
Home Life
Farm & Forest
Land Stewardship
Public Roads
Just for Fun

About

Board
Annual Report
Boundary Map
Bylaws
SRN History
Contact Us
Privacy Policy
Terms of Use
© COPYRIGHT 2015. ALL RIGHTS RESERVED.